Welcome to TSS

Technology Share 4

Construction plan of online leak sealing
 

Instruction:

 

The online leak sealing service is mainly the repair operation in petroleum, petrochemical, electric power, chemical, steel and other related industries. In the case of the plant continue running operation with pressure, cooling, and no stop, the leakage can be eliminated quickly for the factory to save money and the economic loss and environmental pollution caused by the leakage. This project requires the service provider to become a fast response enterprise to maximize the recovery of enterprise losses. Leakage of flange and pipe is the most common leakage in enterprises. In order to ensure the safety of the construction of flanges and pipelines with pressure, and to ensure the design of the fixture and the quality of the online leak sealing, the plan is formulated.

 

1.Engineering personnel received customer needs the service information, first record field condition described by the manufacturer, such as leakage of medium, temperature, pressure.According to the description of Party A's personnel, organize the construction personnel and equipment to rush to the scene in conjunction with the company's safety construction procedures and experience.

 

2.Organization of personnel

 

(1) the construction team must not be less than 3 persons, of whom 1 are group leaders, 1 are safety personnel and 1 are team members. If the construction team did not have a full-time safety officer, the leader of the construction team had to describe the on-site situation telephone to the safety personnel and conduct on-site safety disclosure.

 

(2) construction instruments and mechanical equipment

 

(3) selection of materials

 

It is equipped with the corresponding sealant in accordance with the site temperature and medium described by Party A, and selects several spare sealants according to experience to ensure temporary strain when the description of Party A is different from the scene.

 

3.Investigation and design

(1). After the construction team arrived at the scene, the leaking pipeline was measured in situ.

(2). understand the media, pressure, temperature, design the corresponding effective fixture, prepare for the construction.

(3). According to the description of the site leakage and the investigation of site builders, the jig construction operation method, or metal wire binding, can also be selected according to the situation of the site, and the leakage can be eliminated as soon as possible.

 

4.Operation

 

(1). Fixture installation:

 

Before installing the clamp, all injection valves must be tightened and placed in the "open" position.

 

(2) operators must wear relevant protective equipment.

(3) operators should stand on the upper air outlet or use compressed air to blow the leakage medium aside and reveal the leakage area. The leakage medium can not be directly faced to the personnels.

 

5.Injecting sealant

(1) personnels who operate the injection gun must stand on the side of the injection gun and the injection valve.

 

(2) must connect the injection gun to the injection valve, remove the injection gun and exit the push rod to encrypt the seal. First, the cock on the injection valve must be closed. When the sealant is injected, a certain oil pressure on the injection gun must be applied before opening the cock on the injection valve.

 

(3) when the leakage area is larger or there are more leakage points, the sealant will be injected from both sides of the leak point. Starting from the second injection point, the sealant should be crossed on both sides of the leak point to push forward to the leakage point until the leakage is eliminated.

 

6.Ensure the quality and duration of the project

 

(1). In order to ensure the quality of the project, the process control is carried out, the post inspection is supplemented, and the quality of the project is pre controlled from the aspects of personnel, equipment, materials, preparation before construction and construction process.

(2). the implementation of the responsibility system is strictly followed, so that people, posts and responsibilities. Every leader at the construction site should be assigned a group leader to work out detailed operation rules and post responsibility system. Carry out strict training to the site builders.

 

(3). give full play to the role of quality inspectors in controlling project quality.

(4). equipment: it is the premise of ensuring the quality of construction, must achieve good performance, in order to produce high-quality projects.

 

(5). Materials: only qualified materials can ensure qualified projects. The materials used must be strictly tested before going out.

 

(6). Engineering construction process: strictly carry out construction according to safety construction operation rules.

 

 

7.Security guarantee system

 

(1). Safety production management:

a.Establish and improve the safety production leading group headed by company managers.

b.Establish the responsibility system for safety production at all levels, clear the safety responsibility of their own personnel, implement the safety responsibility, carry out the responsibility and target management, and carry out regular inspection on the implementation of the safety production responsibility.

 

(2). Safety technical measures

A.In order to ensure the smooth implementation of the construction project with pressure plugging, we must resolutely implement the safety management policy of "safety first and prevention first", so as to ensure the safety and health of the workers in the process of production and labor, and to ensure that the property is protected from loss.

B.Strictly enforcing the procedure for examination and approval of special operations.

 

8.The finish of the operation of online leak sealing:

Signing the acceptance check for the opration of online leak sealing.

The warranty period of this project is two years. If there is a leakage again, we promise to repair it again for free.

LATEST NEWS

CONTACT US

Phone: +86-13502033389

Tel: +86-22-63145975

Email:info@tssindustry.com

Add: No.469-101,Xuehai Road,Dagang Industry District,Tianjin,China